UPDATE 7/24/2018
The weather has and will continue to cause delays in the road work schedule.
Wednesday
Road work will continue on Stony Hill, Main Street near Hunting Lane and Minnechaug, Hunting Lane, Old Orchard, Pleasant Street and Pomeroy St.
Thursday (If there is no rain)
Possible paving on Main St from Rice Drive to Minnechaug Access Road. East and westbound traffic will be not be allowed to travel through the Main Street intersection on Tinkham Road. Detours will be set up on Tinkham Rd and Bolles. North and southbound traffic on Main St will be open with alternating traffic. Expect delays.
Friday (If there is no rain)
Possible paving on Stony Hill Rd between Briar Cliff Drive and Sunnyside Terrace. Please use alternate routes as the road will be closed to thru traffic. Expect major delays and detours.
Paving cancellations will continue to be posted on the Town website. Please call DPW at 413-596-2800 ext. 208 with any questions or concerns.