Road Work Schedule
Week of July 29, 2019
The following roads will be paved this summer: Brookmont Drive, Delmor Circle, Edson Drive, Hilltop Drive, Monson Road (Bolles Road to Ridge Road), Monson Road (Glendale Road to Beebe Road), South Mountain Road, Pease Street, and Red Bridge Road. There will be updates on the website with a construction schedule, road closures and detours.
Monday – Expect delays on Monson Road (Bolles Road to Ridge) due to construction work.
Tuesday – Expect delays on Monson Road (Bolles Road to Ridge) and approximately 754 Glendale Road due to construction work.
Wednesday – Expect delays on Brookmont Drive and Red Bridge Road due to road work.
Thursday – Expect delays on Brookmont Drive and Red Bridge Road due to road work.
Friday – None
All the road work stated above is subject to change pending weather and all construction updates will be posted with traffic delays and detours.