Wilbraham Paving and Related Work 2022 Scheduling
July 18 - July 22, 2022
• Stony Hill Road (7/18 – 7/22):
o Drainage work will begin on Stony Hill Road near Glenn Drive.
o One lane traffic, expect delays
o Please seek alternate route
• Blacksmith Road (7/19):
o Driveways aprons will be paved
o Patch work at 37 Blacksmith
o No significant delays are expected
• Brainard Road (7/20):
o Road to be milled.
o Road will be closed to all through traffic
o Detour –Stony Hill Road
• Cottage Ave (7/21):
o Road to be milled.
o One lane traffic from Boston Road to Cottage Ave Bridge.
o Expect Delays, seek alternate route
All scheduled construction is weather dependent and subject to change without notice.
Any questions or concerns should be directed to the DPW office at:
DPW@Wilbraham-MA.gov or (413) 596-2800 ext. 208