Posted on: September 23, 2022

[ARCHIVED] Paving Update for Week of Sept 26th

Wilbraham Paving and Related Work 2022 Scheduling

Monday September 26, 2022
Stony Hill Rd @ Glenn Dr
Drainage work – One lane will be closed with alternating traffic. Expect delays.

Thursday September 29, 2022
Branch Rd – Paving
Closed to through traffic detour to Burleigh Rd.

Friday September 30, 2022
Driveway Aprons – Town wide
No traffic delays.


*****  ADDED 09/27/22  *****

9/27/22 Line Painting (Late Night) 
9/28/22 Line Painting (Late Night)
9/29/22 Paving at Stony Hill near Sunnyside (Alternating Traffic Expect Delays)


All scheduled construction is weather dependent and subject to change without notice.

Any questions or concerns should be directed to the DPW office at:

DPW@Wilbraham-MA.gov or (413) 596-2800 ext. 208 